Mildmay Hotel, Dover
|
Existing Site Notes: The Planning Authority were concerned about allowing an undisguised solution on a building that would impinge upon the view of Dover Castle on entering the town centre.
Due to The Concealment Solution, this site was passed.
|
The Concealment Solution: A structural framework was assembled using GRP box structure and angle bracket. The structure was secured to the top parameter of the building using M10 chemical resin bolts. Additional framework was extended from the rear of the building.
GRP & Foamex panels were then attached to the framework with stitch fasteners and GRP nuts and bolts. The panels were then artworked to match the building’s existing rendering.
|
|
|
All content copyright The Undetectables Ltd - admin
|